Tuesday, February 23, 2010

Construction under progress 23-02-10

Our lady devotees Sis. Shirley and Sis. Amy watching the whole progress under the shade.... the weather is rather hot!
The workers are in the process of nailing the zinc sheet... He requested for more cement bricks... we would send to him as soon as possible

Friday, February 12, 2010

Orang Asli construction progress

He has a good reason to smiles.....
construction in progress



Bro Camon and Bro Albert visited the site today at about 6.45pm ... We have been informed that Tata is trying to get more workers to hasten the work. The family are there and are rather happy and looking forward for their dream house.

Thursday, February 11, 2010

Site Report for Orang Asli House

material delivered on site





2nd Visit 26-01-10






Summary of Reports:
1st Visit - 19-1-2010

Attendance : Bro Albert, Bro Lee Chok. Bro Tommy Soo, Camon, Bro Govind, Bro Hamish & Bro John(from Spore)

Meeting Agenda : Contractor Mr Tata propose for a 20 x 30ft asli house with 3 bed room, 1 kitchen and 1 toilet, estimated contract cost is 5 thousand. Tangkak Bhajan Unit to source for used building Materials.


2nd Visit - 26-1-2010

Attendance : Bro Albert, Bro, Wan, Bro Ah Bok, Bro Lim Choon & son, Bro Tommy, Bro Ong, Bro Camon

1. Negotiate with contractor Mr Tata and agreed wages reduce to RM4 thousand and construction period to be completed in 1 1/2 month.
2. Finalise the housing spec and materials needed
3. Agreed the term and plan to start building in early February 2010
4. Payment by progressive or after completion of construction
(Bro Hamish via telephone conversation have volunteered to bear for wages cost and Tangkak Bhajan Unit would be responsible for all the materials cost. )

3rd Visit - 4-2-2010

Attendance : Bro Camon, Bro Lim, Bro Eu,

- Site visit to view project progress
- Order Sand and granite immediately from Bekoh hardware Shop
- 4 yard of sand and 2 yard granite @50 per yard Total RM300, delivery same afternoon
- Interviewed Orang Asli wife for family information & income
- husband age 33 (1977) wife 35(1975) with 5 children (2 sons & 3 daughters) - age 9,8,6,4 & 9mth
- monthly family income RM300.00 (potong kelapa sawit & kerja kampong)

4th Visit - 8-2-2010

Attendance: Bro Albert & Camon

- Site visit to view the construction progress
- ordered material via Bro. Lee Chok (PL Timber) last week, but not yet delivered
- Immediate call supplier to follow up and promise delivery latest by tomorrow